Question: Solid Constructions, Inc. agreed to construct an apartment building in CM Recto Avenue at a price of P30,000,000. The information relating to costs and billings
Solid Constructions, Inc. agreed to construct an apartment building in CM Recto Avenue at a price of P30,000,000. The information relating to costs and billings for this contract is shown below: Years 2015 2016 2017 Costs incurred to date P7,000,000 P15,000,000 P19,625,000 Estimated costs yet to be incurred 13,000,000 5,000,000 0 Customer billings to date 3,750,000 18,235,125 30,000,000 Collections of billings to date 3,000,000 14,375,650 27,500,000 Assuming Solid uses the cost recovery method, compute the amount of inventory or current liability to be shown in its December 31, 2016 balance sheet.
A. P(3,325,125) current liability
B. P(3,532,125) current liability
C. P(3,235,125) current liability
D. P642,875 inventory