(15) A product has an average weekly demand of 75 with an EOQ of 305 . The lead time is 2 weeks. The inventory holding cost is $2 per unit per week. The shortage cost is $18 per unit over the order cycle. The demand forecast error is normally distributed with a standard deviation of 25 each week. a. (10) What is the safety stock needed to mitigate the risk of high demand? b. (5) It is proposed to reduce the lead time to 1 week. This will cost $50 per order cycle. Does the reduction in safety stock inventory cost justify this cost