Question: solve completely. The PERT Network beiow has activities (A,B,.H) and each has duration, shown inside the circle (A+4,F=2. Answer the sollowing three questions by entering

solve completely.
solve completely. The PERT Network beiow has activities (A,B,.H) and each has
duration, shown inside the circle (A+4,F=2. Answer the sollowing three questions by

The PERT Network beiow has activities (A,B,.H) and each has duration, shown inside the circle (A+4,F=2. Answer the sollowing three questions by entering ONLY a number (e:, 35 or 3 or 7 ) as it will be automatically graded: - Verat is the EF for activity G? What is the LF for activity F ? Question 52 What I the LF for activity G