Question: The PERT Network below has activities (A,B....H) and each has duration, shown inside the circle (A-4, F-2 H-6) Answer the following three questions by

The PERT Network below has activities (A,B....H) and each has duration, shown

 inside the circle (A-4, F-2 H-6) Answer the following three questions by

The PERT Network below has activities (A,B....H) and each has duration, shown inside the circle (A-4, F-2 H-6) Answer the following three questions by entering ONLY a number (e.g. 35 or 3 or 7) as it will be automatically graded: What is the EF for activity G? START H What is the LF for activity F? Question 52 What I the LF for activity G?