Question: solve it fast A project has been defined to contain the following list of activities, along with their precedence relations and time and cost estimates
A project has been defined to contain the following list of activities, along with their precedence relations and time and cost estimates for the activity durations. Use the normal durations to compute the earliest start (ES), earliest finish (EF), latest start (LS), latest finish (LF) and slack on each of the activities. What is the LS of activity G? a. 21 b. 25 c. 22
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
