Question: solve it plz A project has been defined to contain the following list of activities, along with their precedence relations and time and cost estimates

solve it plz
solve it plz A project has been defined to contain the following

A project has been defined to contain the following list of activities, along with their precedence relations and time and cost estimates for the activity durations. Use the normal durations to compute the earliest start (ES), oarliest finish (EF), latest start (LS), latest finish (LF) and slack on each of the activities What is the LF of activity E? a. 25 b. 19 c. 18