Question: solve plz A project has been defined to contain the following list of activities, along with their precedence relations and time and cost estimates for
A project has been defined to contain the following list of activities, along with their precedence relations and time and cost estimates for the activity durations. Use the normal durations to compute the eariest start (ES), eariest finish (EF), latest start (LS), latest finish (LF) and siack on each of the activitios. What is the ES of activity D? i. 10 b. 24 c. 15