Question: solve Problems 4.15 Modified (change lead-time of item C from 1 week to 2 weeks) 4.15. Given the following product tree, explode, offset, and determine
solve Problems 4.15 Modified (change lead-time of item C from 1 week to 2 weeks)

4.15. Given the following product tree, explode, offset, and determine the gross and net requirements. All lead times are 1 week, and the quantities required are shown in parentheses. The master production schedule calls for the completion of 100 As in week 4 and 50 in week 5 . There are 300 Bs scheduled to be received in week 1 and 200 Ds in week 3 . There are also 20 As available