Question: Solve the following case and build a diagramming technique using the Critical Path Method (CPM). The table below lists the time estimates and immediate predecessor(s)

Solve the following case and build a diagramming technique using the Critical Path Method (CPM).

The table below lists the time estimates and immediate predecessor(s) for each activity in a product marketing project that is to be scheduled using CPM.

Activity

1

2

3

4

5

6

7

8

9

Activity time (days)

1

4

3

7

5

4

6

9

4

Immediate predecessor

-

1

1

1

2

3, 4

5, 6

4

7,8

1.Draw the CPM network diagram for the project, labeling all activities and times

2.Determine the critical path and the expected duration of the project.

3.Perform a forward pass and backward pass through the network to determine the slack time for each activity

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!