Question: Solve the following case and build a diagramming technique using the Critical Path Method (CPM). The table below lists the time estimates and immediate predecessor(s)
Solve the following case and build a diagramming technique using the Critical Path Method (CPM).
The table below lists the time estimates and immediate predecessor(s) for each activity in a product marketing project that is to be scheduled using CPM.
| Activity | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
| Activity time (days) | 1 | 4 | 3 | 7 | 5 | 4 | 6 | 9 | 4 |
| Immediate predecessor | - | 1 | 1 | 1 | 2 | 3, 4 | 5, 6 | 4 | 7,8 |
1.Draw the CPM network diagram for the project, labeling all activities and times
2.Determine the critical path and the expected duration of the project.
3.Perform a forward pass and backward pass through the network to determine the slack time for each activity