Question: Solve the following case and build a diagramming technique using the Critical Path Method (CPM). Activity 1 2 3 4 5 6 7 8 9
Solve the following case and build a diagramming technique using the Critical Path Method (CPM).
| Activity | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
| Activity time (days) | 1 | 4 | 3 | 7 | 5 | 2 | 6 | 9 | 4 |
| Immediate predecessor | - | 1 | 1 | 1 | 2 | 3, 4 | 5, 6 | 4 | 7,8 |
1. Draw the CPM network diagram for the project, labeling all activities and times.
2. Determine the critical path and the expected duration of the project.
3. Perform a forward pass and backward pass through the network to determine the slack time for each activity