Question: solve this An agile team has started work on an iteration, planning to complete user Stories X, Y, and Z. Story X is estimated at
solve this
An agile team has started work on an iteration, planning to complete user Stories X, Y, and Z. Story X is estimated at 4 points, story Y at 3 points, and story Z at 5 points. At the end of the iteration, stories X and Y are 100% complete, but Z is only 60% complete. Agile teams generally consider user stories either 0% done or 100% done. Therefore, Z is not counted toward the iteration's velocity. What is the total velocity for this iteration? 8 points 5 points 7 points 12 pointsStep by Step Solution