Question: solve this An agile team has started work on an iteration, planning to complete user Stories X, Y, and Z. Story X is estimated at

solve this

An agile team has started work on an iteration, planning to complete user Stories X, Y, and Z. Story X is estimated at 4 points, story Y at 3 points, and story Z at 5 points. At the end of the iteration, stories X and Y are 100% complete, but Z is only 60% complete. Agile teams generally consider user stories either 0% done or 100% done. Therefore, Z is not counted toward the iteration's velocity. What is the total velocity for this iteration? 8 points 5 points 7 points 12 points

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!