Question: SOLVE USING EXCEL FORMULA Problem 3 (3 POINTS) Building a backyard swimming pool consists of nine major activities. The activities are as shown in the

SOLVE USING EXCEL FORMULA

Problem 3 (3 POINTS) Building a backyard swimming pool consists of nine major activities. The activities are as shown in the network diagram. Note: There are 3 paths in this network Assume the activity time estimates (in days) for the swimming pool construction project are as follows: Activity Optimistic (o) Most Likely (m) Pessimistic (p)

ACTIVITY OPTIMISTIC(0) MOST LIKELY(M) PESSIMISTIC(P)
A 3 5 6
B 2 4 7
C 5 6 7
D 7 9 11
E 2 6 8
F 2 5 7
G 5 6 8
H 6 8 10
I 3 4 6

What is the probability that the project can be completed within a deadline of 18 days? Assumption: If the z-value of a path is greater than or equal to 3, then there is a 100% probability that the path will be done as per its expected time.

SOLVE USING EXCEL FORMULA Problem 3 (3 POINTS)

problem) Hint: There are THREE paths in this network (I am giving this information so that you minimize your errors). B A D > E F END G H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!