Question: SOLVE USING EXCEL FORMULA Problem 3 (3 POINTS) Building a backyard swimming pool consists of nine major activities. The activities are as shown in the
SOLVE USING EXCEL FORMULA
Problem 3 (3 POINTS) Building a backyard swimming pool consists of nine major activities. The activities are as shown in the network diagram. Note: There are 3 paths in this network Assume the activity time estimates (in days) for the swimming pool construction project are as follows: Activity Optimistic (o) Most Likely (m) Pessimistic (p)
| ACTIVITY | OPTIMISTIC(0) | MOST LIKELY(M) | PESSIMISTIC(P) |
| A | 3 | 5 | 6 |
| B | 2 | 4 | 7 |
| C | 5 | 6 | 7 |
| D | 7 | 9 | 11 |
| E | 2 | 6 | 8 |
| F | 2 | 5 | 7 |
| G | 5 | 6 | 8 |
| H | 6 | 8 | 10 |
| I | 3 | 4 | 6 |
What is the probability that the project can be completed within a deadline of 18 days? Assumption: If the z-value of a path is greater than or equal to 3, then there is a 100% probability that the path will be done as per its expected time.

Step by Step Solution
There are 3 Steps involved in it