Question: Sometimes the scope of a project creeps and changes until the product you design is far different from the original concept ( e . g

Sometimes the scope of a project creeps and changes until the product you design is far different from the original concept (e.g., Bradley Fighting Vehicle). What tool in the Design phase of DMAIC can help to address scope early in the project?
Question 6 options:
cause-and-effect diagram
Work Breakdown Structure
Charter
process map
Pareto chart