Question: Squirt's assembly unit has decided to use a p - Chart with an alpha risk of 5 % to monitor the proportion of defective copper

Squirt's assembly unit has decided to use a p-Chart with an alpha risk of 5%
to monitor the proportion of defective copper wires produced by their production process. The quality control manager randomly samples 150
copper wires at 12
successively selected time periods and counts the number of defective copper wires in the sample.
Table
Sample Defects
18
210
313
412
57
611
710
89
912
1014
1110
1212
Control Chart
Step 1 of 8: What is the Center Line of the control chart? Round your answer to three decimal places.