Question: s/secured#lockdown Given the project within the table below, calculate the following: the X Activity Duration (hours) Immediate Predecessors A 4 B 13 00 , D

s/secured#lockdown Given the project within the
s/secured#lockdown Given the project within the table below, calculate the following: the X Activity Duration (hours) Immediate Predecessors A 4 B 13 00 , D 7 E 2 B.C F 3 3 DE F G 7 a. What is the project length? (Select] b. What activities are on the critical path? Select C. How much slack in in activity B? [Select) d. What is the Late Start / Late Finish for activity D? Select) f. What if activity D was delayed by 8 hours inow taking 15 hourst what ouer would it have on the overall project? Select! Sto sharing