Question: Given the project within the table below, calculate the following: Activity Duration ( hours ) Immediate Predecessors A 4 None 0 0 5 None 1
Given the project within the table below, calculate the following: Activity Duration hours Immediate Predecessors A None None A D B C E D F E G E F F a What is the project's minimum completion time? Select b What is the critical path in the project? Select c What is the slack in activity BSelect D BC E D F E G E F a What is the project's minimum completion time? Select b What is the critical path in the project? Select c What is the slack in activity BSelect d What is the Early Start and Early Finish for Activity DSelect e What is the Late Start and Late Finish for activity BSelect f What would happen to the overall project length if activity C now took an additional hours to complete, now taking a total of hours? Select
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
