Question: ssignment Two International banks are integrating two financial processing software systems as a result of their merger. Preliminary analysis and interviews with all parties involved

ssignment Two International banks are integrating
ssignment Two International banks are integrating
ssignment Two International banks are integrating
ssignment Two International banks are integrating two financial processing software systems as a result of their merger. Preliminary analysis and interviews with all parties involved resulted in the following project Information. The systems integration team" for this project plans to define and manage the project on two levels. The following table shows the crash times and normal and crash costs for the international bank systems Integration project. All times are in weeks Crash Immediate Predecessors Time Activity Normal Time 2 3 5 3 B A C D E A B, C E EF D,G,H 2 2 3 2 4 5 5 Normal Cost $1,250 4,100 2,100 5,400 2,500 2,150 4,700 3,100 8,000 Crash Cost $1,250 5,600 3,900 5.900 3,800 2,950 8.900 3,800 10,600 G H 2 8 7 1 6 5 a. Choose the correct network for the project. The correct works Assignment B E H D C H H CH b. Identify the critical path The critical path is What is the total project completion time? Round your answer to the nearest whole number d. What is the lowest cout solution if the bank wants to complete the project two weeks early Round your answer for the project duration to the nearest whole number and the and for the total cost to the nearest dollar The total cost of oon) week project completion schedule is s

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!