Question: SSS Manufacturing has a five station work cell. Station 1 has a production capacity of 6 per hour. Station 2 has a production capacity of

SSS Manufacturing has a five station work cell. Station 1 has a production capacity of 6 per hour. Station 2 has a production capacity of 5 per hour. Station 3 has two identical machines, each of which has a production capacity of 4 per hour (each unit only needs to be processed on one of the two machines). Station 4 has a production capacity of 12 per hour. Station 5 has a production capacity of 7.5 per hour. Which station is the bottleneck station?
Station 4
Station 3
Station 5,
Station 2
Station 1