Question: Stakeholder Register It is estimate that there will be a need for one full time project manager, two full time business analysts for first two

Stakeholder Register It is estimate that there will be a need for one full time project manager, two full time business
analysts for first two months, two full time senior programmers for the third and fourth month of
project, three full time junior programmers for fourth month and one full time technical writer for
the last two months. Create a resource histogram representing the given information.