Question: Standard Time ( 5 marks) A large cable company received a shipment of audio video cables with the wrong connectors. The error was made by

Standard Time ( 5 marks)

A large cable company received a shipment of audio video cables with the wrong connectors. The error was made by the cable companys specifications provided to the overseas supplier. The operations manager calculates that it would be cheaper to manually change the connectors rather than the supplier re-doing or fixing the cables. The manager observes the first set of workers pulled aside to change the cables and from these observations will set a standard time. The observations are as follows for workers to each change the connectors on sets of 20 cables.

Observation

Time (min)

1

7.17

2

7.23

3

6.98

4

7.05

5

7.54

6

7.33

7

7.11

8

7.27

9

7.09

10

6.99

The manager will use a performance rating factor of .95 and an allowance factor of .04.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!