Question: Standard times: 2 . 0 min , 1 , 5 min, 3 . 0 min, 2 . 2 min You have the following additional information:
Standard times:
min
min,
min,
min You have the following additional information: Line efficiency is expected to be
and transfer time between workstations is
seconds
repositioning time
Find the following:
Required cycle time
Service time
Manning level
Work content time
Actual line efficiency
How many operators should be on each operation?
With that set up what will be the actual production of the line per day?
What is takt Time?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
