Question: Station 1 ' s process time is 9 minutes / unit . Station 2 ' s process time is 1 0 minutes / unit .

Station 1's process time is 9 minutes/unit. Station 2's process time is 10 minutes/unit. Station three has two identical machines, each of which process a unit in 12 minutes (each unit only needs to be processed on one of the two machines). Station 4's process time is 5 minutes/unit. Station 5's process time is 8 minutes/unit. Which station is the bottleneck station?