Question: Statis > Moving to another question will save this response. CW Question 6 Slegmeyer Corp. is considering a new inventory system, Project A that will
Statis > Moving to another question will save this response. CW Question 6 Slegmeyer Corp. is considering a new inventory system, Project A that will cost $2.400.000 The system is expected to generaleve cash flows ready in year one, 5900.000 in year two, $1.000.000 in year three, and $1.200.000 in year four, Segmeyer's required to retumis 18% What is the internal rate of return of this project? 12.50% 16.67% 19.31% 23.129 Moving to another question will save this response Close Window # 3 % 5 0 2 T R w E