Question: Status Reporting[WLOs: 2, 4] [CLOs: 2, 4, 6] Given the following project network, baseline, and status information, develop status reports for periods 2, 4, 6,

Status Reporting[WLOs: 2, 4] [CLOs: 2, 4, 6]

Given the following project network, baseline, and status information, develop status reports for periods 2, 4, 6, 8, and complete the performance indexes table. Calculate the forecasted estimate at completion (EAC) and the forecasted variance at completion (VAC). Based on your data, what is your assessment of the current status of the project? Is it at completion?

Paths

Budget Allocations

ID

Budget ($000)

1

2

3

4

5

6

7

8

9

10

11

12

A

40

10

10

10

10

B

32

8

4

8

4

8

C

48

12

12

12

12

D

18

6

2

2

2

6

E

28

8

8

12

F

40

20

20

Total

206

18

14

18

14

20

26

22

26

2

6

20

20

Cumulative

18

32

50

64

84

110

132

158

160

166

186

206

Status Reports

Status Report: Ending Period 2

($000)

Task

% Complete

EV

AC

PV

CV

SV

A

75%

-----

25

-----

-----

-----

B

50%

-----

12

-----

-----

-----

Cumulative Totals

-----

37

-----

-----

-----

Status Report: Ending Period 4

($000)

Task

% Complete

EV

AC

PV

CV

SV

A

100%

-----

35

-----

-----

-----

B

100%

-----

24

-----

-----

-----

Cumulative Totals

-----

59

-----

-----

-----

Status Report: Ending Period 6

($000)

Task

% Complete

EV

AC

PV

CV

SV

A

100%

-----

35

-----

-----

-----

B

100%

-----

24

-----

-----

-----

C

75%

-----

24

-----

-----

-----

D

0%

-----

0

-----

-----

-----

E

50%

-----

10

-----

-----

-----

Cumulative Totals

-----

93

-----

-----

-----

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!