Question: Step 6 8 seconds 30% Yes No Step 1- 18 seconds Step 2 120 seconds Step 3 35 seconds Data inconsistency?0 seconds Step 4 database?

 Step 6 8 seconds 30% Yes No Step 1- 18 seconds

Step 6 8 seconds 30% Yes No Step 1- 18 seconds Step 2 120 seconds Step 3 35 seconds Data inconsistency?0 seconds Step 4 database? 55% No 45% Yes Assuming the probability of errors after the first time through the rework loop is zero, what is the average cycle time for this process? about 325 seconds about 318 seconds about 323 seconds about 329 seconds