Question: Step A: Average time 5 minutes, stdev = 1.2 minutes Step B: Average time 9 minutes, stdev = 0.9 minutes Step C: Average time 11
Step A: Average time 5 minutes, stdev = 1.2 minutes
Step B: Average time 9 minutes, stdev = 0.9 minutes
Step C: Average time 11 minutes, stdev = 2.1 minutes
Given the above data on a three-stage production process, what is the probability step C takes longer than step B?