Question: Step A has a processing time of 0.85 minute per unit, but no setup is required. Step B has a processing time of 0.18 minute

Step A has a processing time of 0.85 minute per unit, but no setup is required. Step B has a processing time of 0.18 minute per unit, but a setup time of 11 minutes is required per batch.
- Suppose units are produced in batches of12. What is the capacity of the process (in units per minute)?
- What is the batch size that maximizes the flow rate of this process with minimal inventory? Assume there is ample demand. (Round up your final answer to nearest integer)