Question: Stephanie, a project manager of a project in your program, is about to close her project. She has asked you, the program manager, what will
Stephanie, a project manager of a project in your program, is about to close her project. She
has asked you, the program manager, what will happen to the deliverable, a program benefit,
of her project if its not going immediately into operations. What is the most likely response
you can give Stephanie?
a Her deliverable is considered an incremental benefit and will flow into the benefits of
the program.
b Her deliverable is considered an incremental benefit and will be held until the
program is closed and all the benefits from the program are ready to be moved into
operations.
c Her project is considered an incremental benefit and will be recorded in the benefits
register.
d Her project deliverable is considered a tiered deliverable, and her project will serve as
an input to another project whose deliverable will flow into operations.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock