Question: Stephen, the project manager, is estimating the cost for his project using three point estimates. Which of the following regarding three point estimates is FALSE?
Stephen, the project manager, is estimating the cost for his project using three point estimates. Which of the following regarding three point estimates is FALSE?
Group of answer choices
It improves the accuracy of single point activity cost estimates
It considers most likely estimates
It considers optimistic cost estimates
It calculates the required reserve for the project