Using the table below, draw the network diagram and answer the questions. 1. How many paths are
Fantastic news! We've Found the answer you've been seeking!
Question:
Using the table below, draw the network diagram and answer the questions.
1. How many paths are in the network, and what are they? (1 mark)
2. What is the critical path and its duration? (1 mark)
3. What is the float on activity U? (1 mark)
4. What is the impact to the project if activity B takes three weeks longer than planned? (1 mark)
Activity | Predecessor | Estimate in Weeks |
Start | - | 0 |
C | Start | 6 |
B | Start | 4 |
P | Start | 3 |
A | C,B,P | 7 |
U | P | 4 |
T | A | 2 |
R | A | 3 |
N | U | 6 |
End | T,R,N | 9 |
Related Book For
Posted Date: