Question: stion 37 Task ID Predecessor Duration (days) 3 Resources Required 1 2 3 4 1 3 3 2 1 5 6 7 8 1 1

stion 37 Task ID Predecessor Duration (days) 3
stion 37 Task ID Predecessor Duration (days) 3 Resources Required 1 2 3 4 1 3 3 2 1 5 6 7 8 1 1 2,3 4 4 $ 6,7 2 2 1 3 1 2 2 2 1 3 the earliest start for the project above is O day, and further asume that the latest finish is equal to earliest finish. The maximum available number of resource is 3 Without a rente constrained schedule, the resource load on day 4 would be