Question: Student Name: Student No: Below is a project WBS with cost apportioned by percent for each work package. If the total project cost is estimated

Student Name: Student No: Below is a project WBS with cost apportioned by percent for each work package. If the total project cost is estimated to be $800,000, what are the estimated costs for the following deliverables? Router systems project Cost$800,000 Definition Design Implementation 10%40%50% Objectives Requirements -house Customer testing & review 4%6 testing 40%10% Outputs Interfaces Programming Inputs 3%9%3%22%3% a Design? b Programming ? In-house testing ? What weaknesses are inherent in this estimating approach ?