Question: Student's Name: The earliest start time for a specific activity must be the latest of all the earliest finish times of all the activities leading
Student's Name:
The earliest start time for a specific activity must be the latest of all the earliest finish times of all the activities leading directly into that specific activity.
a earlier than
b the same as
c the same as or later than
d later than
Calculate the earliest start for Task D if one of its predecessors, Task A finishes on day its other predecessor. Task finishes on day and the duration of Task is days.
a day
b day
c day
d Cannot be calculated based upon information given.
Calculate the earliest finish for Task if one of its predecessors, Task finishes on day its other predecessor, Task finishes on day and the duration of Task is days.
a day
b day
c day
d Cannot be calculated based upon information given.
The total completion time is days. Task is planned to take seven days. Task is planned to take five days. Task is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed inst seven days. What are the ES and EF times for Task B now that Task is complete?
a
b
c
d
Schedule control involves four steps. Place these steps in their proper by stating the letter sequence of their proper order.
A Analyzing the schedule to determine which areas may need corrective
Recalculating the schedule to evaluate the effects of the planned co actions
C Revising the plan to incorporate the chosen corrective actions
Deciding what specific corrective actions should be taken
a
b
c
d
Step by Step Solution
There are 3 Steps involved in it