Question: The earliest start time for a specific activity must be q , the latest of all the earliest finish times of all the activities leading

The earliest start time for a specific activity must be q, the latest of all the earliest finish times of all the activities leading directly into that specific activity.
a. earlier than
b. the same as
c. the same as or later than
d. later than
 The earliest start time for a specific activity must be q,