Question: The earliest start time for a specific activity must be q , the latest of all the earliest finish times of all the activities leading
The earliest start time for a specific activity must be the latest of all the earliest finish times of all the activities leading directly into that specific activity.
a earlier than
b the same as
c the same as or later than
d later than