Question: [Study Guide] Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day

[Study Guide] Two critical path activities are
[Study Guide] Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ....... should be crashed first, adding to project cost. Activity B Normal Time Normal Cost Crash Time Crash Cost 4 days $6,000 3 days $8,000 6 days $4,000 5 days $6,000 B: $1.000 B: $8,000 C: $2.000 C: $6,000 C: $1.000 Next Previous