Question: SUBJECT - OPEARTING SYSTEMS QUESTION 1 Process Arrival time Execution time A 0 9 B 2 6 C 3 5 D 5 8 E 7

SUBJECT - OPEARTING SYSTEMS

QUESTION 1

Process

Arrival time

Execution time

A

0

9

B

2

6

C

3

5

D

5

8

E

7

2

F

7

8

Develop the scheulde (time diagram) for the following 4 cases.

First-Come-First-Served (FCFS)

Round Robin

Shortest Process Next (SPN)

Shortest Remaining Time (SRT)

SOLUTION

QUESTION 2

Develop the schedule diagram for the Earliest Deadline scheduling by using competition deadline.

Process

Arrival time

Execution time

Ending Deadline

A(1)

0

10

20

A(2)

20

10

40

A(3)

40

10

60

B(1)

10

20

40

B(2)

50

20

80

B(3)

80

20

120

B(4)

120

20

160

C(1)

20

30

60

C(2)

70

30

100

SOLUTION

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!