Question: Submit test point(s) possible Consider the project described by the project digraph shown on the right, and assume to schedule this project using N =

Submit test point(s) possible Consider the project described by the project digraph shown on the right, and assume to schedule this project using N = 3 A3) BG) C3) D3 processors. Complete a through c. 0 0- E(5) F(5) START(O) END(0) G(5 H(5) 1(5 ) J (5) (a) Use the decreasing-time algorithm to schedule the project. Show the timeline for the project and the finishing time Fin. Choose the correct timeline below. P E(5) F(5) H(5) E(5) FIST A(3 D(3 O A. P2 G(5) B(3) C(3) D(3 OB P G S H(5) P 3 A(3 1(5 J(5) Pa 15 J (5) C(3 un- 10 15 20 10 15 20 25 1:1 P 1(5 P E(5 J(5) 4/ 1:1 O C. P2 G(5) B(3) C(3) D 3) OD. P G(5) H(5) E(5) F(5) H(5) P B(3) D(3) 10 15 20 10 15 20 am What is the project's finishing time