Question: succes ques help control a project's progression? 13. Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure
ques help control a project's progression? 13. Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and identify the critical path for the project. Can the project be completed in 40 weeks? Assume that activity A actually finished at 3 weeks, Activity B Activity E 10 Activity A Activity D Activity G 15 12 ActivityhH Activity C Activity F 20