Question: Summit Manufacturing employs the process displayed below. a ) which operation is the bottleneck? b ) what is the system s bottleneck time? c )

Summit Manufacturing employs the process displayed below.
a) which operation is the bottleneck?
b) what is the systems bottleneck time?
c) what is the throughput time for the overall system? Sanding
15 min/unit
Welding
25 min/unit
Assembly
20 min/unit
d) suppose that the welding machine is replaced with one that is twice as fast. What
are the new system bottleneck and throughput times, respectively?