Question: Super Computer Co . provided the following summary regression results for Maintenance Costs: Number of Set - ups: Coefficient Standard Error t - Value Intercept

Super Computer Co. provided the following summary regression results for Maintenance
Costs:
Number of Set-ups: Coefficient Standard Error t-Value
Intercept $36,939.77 $56,504.880.65
Slope coefficient $ 361.91 $152.932.37
R
2=0.36; Estimated use =54 set-ups
Number of Machine Hours: Coefficient Standard Error t-Value
Intercept $30,654.86 $23,569.510.16
Slope coefficient $ 56.76 $7.827.25
R
2=0.84; Estimated use =1,600 machine hours
Currently Maintenance Costs are estimated using the High Low method based on Direct Labor Hours
using the following data:
Direct Labor hours Maintenance Costs
Highest observation of cost driver 2,500 $300,000
Lowest observation of cost driver 1,500 $220,000
a. Using the High-Low method, what is the estimate of the Maintenance Costs when 1,300 Direct Labor
hours are used?
b. Based on the regression information above indicate which cost driver (Set-ups or Machine Hours) is
the better cost driver? Why is this cost driver best?
c. Using the regression information above and the cost driver from b. estimate Maintenance Costs for
the coming year.
d. Which of your estimates (a. or c.) is the more accurate estimate of Maintenance Costs? Why?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!