Question: Suppose a particular project has an expected completion time of 3 0 days; in other words, the critical path takes 3 0 days to finish.

Suppose a particular project has an expected completion time of 30 days; in other words, the
critical path takes 30 days to finish. Further, the variance of the critical path is 25. Based on this
information, please answer the following questions:
Find the probability that the project:
Would be completed within 40 days
Would take longer than 40 days to finish
Would be completed within 20 days
Would take longer than 20 days to finish

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!