Question: Suppose a proposal is made to construct a new interstate highway through a plot of undisturbed land. Assume that the costs and benefits associated
Suppose a proposal is made to construct a new interstate highway through a plot of undisturbed land. Assume that the costs and benefits associated with the proposal are as follows: Year 1 2 3 Benefits (S millions) 200 600 800 Costs ($ millions) 500 200 800 If the discount rate is 3 percent, calculate the present value of the net benefits for this project. Based on the results, would you support this project?
Step by Step Solution
3.41 Rating (160 Votes )
There are 3 Steps involved in it
The formula for calculating the present value of a future payment is PV FV 1 r... View full answer