Question: Suppose a software development project using the Waterfall Model has the following phases: Requirements Analysis ( 2 months ) Design ( 3 months ) Implementation
Suppose a software development project using the Waterfall Model has the
following phases:
Requirements Analysis months
Design months
Implementation months
Testing months
Deployment month
Calculate the total duration of the project and identify any potential issues that might arise
due to the sequential nature of the Waterfall Model.