Question: Suppose an activity is defined as a fixed work activity in MS Project. The activity requires the use of a resource called Worker. Currently, the
Suppose an activity is defined as a fixed work activity in MS Project. The activity requires the use of a resource called Worker. Currently, the activitys parameters are: Duration = 4 days Units = 300% Work = 96 hours Calendar time = 8 hours per day If the value of Work is changed from 96 hours to 60 hours, the value of Units becomes
Group of answer choices
< 200%
>= 200% and < 300%
>= 300% and < 400%
>= 400%
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
