Question: Suppose an activity is defined as a fixed work activity in MS Project. The activity requires the use of a resource called Worker. Currently, the

Suppose an activity is defined as a fixed work activity in MS Project. The activity requires the use of a resource called Worker. Currently, the activitys parameters are: Duration = 4 days Units = 300% Work = 96 hours Calendar time = 8 hours per day If the value of Work is changed from 96 hours to 60 hours, the value of Units becomes

Group of answer choices

< 200%

>= 200% and < 300%

>= 300% and < 400%

>= 400%