Question: Suppose an activity is defined as a fixed units activity in MS Project. The activity requires the use of a resource called Worker. Currently, the
Suppose an activity is defined as a fixed units activity in MS Project. The activity requires the use of a resource called Worker. Currently, the activitys parameters are:
Duration = 4 days
Units = 300%
Work = 96 hours
Calendar time = 8 hours per day
If the value of Duration is changed from 4 days to 5 days, the value of Work becomes:
< 95 hours
>= 95 hours and < 105 hours
>= 105 hours and < 115 hours
>= 115 hours