Question: Suppose an activity is defined as a fixed units activity in MS Project. The activity requires the use of a resource called Worker. Currently, the

Suppose an activity is defined as a fixed units activity in MS Project. The activity requires the use of a resource called Worker. Currently, the activitys parameters are:

Duration = 4 days

Units = 300%

Work = 96 hours

Calendar time = 8 hours per day

If the value of Duration is changed from 4 days to 5 days, the value of Work becomes:

< 95 hours

>= 95 hours and < 105 hours

>= 105 hours and < 115 hours

>= 115 hours