Question: Suppose for a design project, the completion tine is estimated as normally distributed with a mean of 3 5 days with standard deviation of 1

Suppose for a design project, the completion tine is estimated as normally distributed with a mean of 35 days with standard deviation of 10 days. The project manager wishes to quote a project completion time to her CEO with a 98% confidence level. She would quote a completion time of: 45 days. 15 days. 25 days. 56 days.