Question: 31. Suppose for a design project, the completion time is estimated as normally distributed with a mean of 35 days with standard deviation of 10

31. Suppose for a design project, the completion time is estimated as normally distributed with a mean of 35 days with standard deviation of 10 days. The project manager wishes to quote a project completion time to her CEO with a 98% confidence level. She would quote a completion time of:

45 days

25 days

56 days

15 days