Question: Suppose that a MAX problem contained the following constraint: 5 x + 8 y 4 0 . Then which of the following statements is true?

Suppose that a MAX problem contained the following constraint: 5x +8y 40. Then which of the following statements is true?
For the point (1,4), the slack for this constraint would have a value of 3.
For the point (8,5), the slack for this constraint would have a value of 40.
For the point (4,2), the slack for this constraint would be zero.
For the point (4,2.5), the slack for this constraint would be a positive value. 2.Consider a linear programming model with the objective of profit maximization. Let Xi = the number of units to produce of product i. The objective function coefficients should typically be:
Group of answer choices
profit per unit.
selling price per unit.
variable cost per unit.
revenue per unit. 3.There are 50 hours of production time available in a given department. The department produces three products and their production times are as follows: (X8 minutes),(Y4 minutes),(Z7 minutes). The correct resource availability constraint is:
Group of answer choices
.13X +.06Y +.11Z 50
8X +4Y +7Z 3000
8X +4Y +7Z 50
8X +4Y +7Z 30004.Any change in the values for the RHS (Right Hand Side) of a binding constraint of an LP problem will:
Group of answer choices
change the slope of the that constraint
change the slope of the objective function
not change the slope of the constraint but move it parallel to the original
not change the feasibility region 5.Which of the following statements is FALSE regarding employee staffing applications?
Group of answer choices
It is possible to have multiple optimal solutions in employee staffing applications.
The goal of employee staffing problems is typically to determine how many employees need to start their work at the different starting times permitted.
Employee staffing problems can be formulated as assignment problems.
The employee staffing problem is a extension of the product mix problem.
Based on the requirements and constraints, it is possible for an employee staffing problem to become infeasible. 6.Consider the following constraint: X140. This implies that at most 40 units of product X1can be produced.
Group of answer choices
True
False 7. The "Sinking Fund" problem can be classified as a multi-period linear programming application.
Group of answer choices
True
False 8.Consider the following linear programming model:
Max X21+ X2+3X3
Subject to:
X1+ X23
X1+ X21
X1, X20
This problem violates which of the following assumptions?
Group of answer choices
certainty
integrality
proportionality
linearity
divisibility 9. A linear programming model generates an optimal solution with fractional values. This solution satisfies which basic linear programming assumption?
Group of answer choices
certainty
divisibility
proportionality
linearity
non-negativity

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!