Question: Suppose that a team of 6 software developers are working on a project using the Kanban methodology. The team is a cross functional team of
Suppose that a team of software developers are working on a project using the Kanban methodology.
The team is a cross functional team of equal expertise and talent consisting analyst as a customer proxy,
developers and testersdeployment managers. Consider the arrival times and effort requirements of
the following tasks assume that the tasks have no interdependencies:
ap By using the Kanban board template below, please draw the situation of Kanban board at
the end of Day and You may indicate a group of tasks as TXTY such as TT for T
T and T
Day :
Day :
Day :
Day :
bp How many days it requires for the team to finish the enlisted tasks if they use the Kanban board template depicted in a
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock