Question: Suppose that in a binary programming model for project selections, there are a total of five projects available for selection. Write the following constraint in
Suppose that in a binary programming model for project selections, there are a total of five projects available for selection. Write the following constraint in the standard form:
"If projects 1 and 3 are selected, then project 4 cannot be selected."
Suppose that in a binary programming model for project selections, there are a total of five projects available for selection. Write the following constraint in the standard form:
"If projects 1 and 3 are selected, then project 4 cannot be selected."
X4 X1 + X3
X1 + X3 + X4 2
X1 + X3 + X4 2
X1 + X3 - X4 3
X4 X1 + X3